LTPBR As-Built Protocol

The LTPBR As-Built Protocol is a survey of built structures. Many LTPBR projects are field fit during construction, and the structures that are ultimately built may differ from what was originally specified in an LTPBR design. As-Built surveys are used to document the location and types of structures as they are built.

The purpose of this protocol is track structure counts for reporting as well as types and locations for reference in designing future phases of the project. Tracking features as they were built also allows us to see and understand structure dynamics. You can see where structures fail, where they survive, as well as which ones act as a collection point for failed structures and other wood in the system.

Protocol Summary

AttributeValue
NameAs-Built Protocol
StatusProduction Grade
Version1.0
XML URLhttps://github.com/Riverscapes/RiverscapesXML/blob/master/QRiS/protocols/as_built_protocol.xml
CitationWeber N., Wheaton J.M., Shalcross A., Al-Chokhachy R, Bailey P., Bartelt K., Bennett S., Bouwes B., Bouwes N., Gilbert J., Dickard M., Heitke J., Jordan C., Glassic H., MacFarlane W.W., Miller S., Saunders C., Whitehead K. 2024. Low-Tech Process-Based Restoration Design and Monitoring Protocol: Standard Methods for Developing Project Designs and Assessing Riverscape Health. Version 2.0. Prepared by Anabranch Solutions and Utah State University Riverscapes Assessment and Monitoring Lab. Prepared for the Bureau of Land Management. Logan, UT. 81 pp. DOI: 10.5281/zenodo.13769899
AuthorNick Weber

Layers

This protocol has three layers. Two different options to collect structures and an observation layer for recording other information pertinent to the survey. Users can collect structure points, structure lines, or a combination of both for their survey. Structure lines may be more useful in the case of representing the actual geometries of structures and finding their lengths. Structure points are simply the location of the structure.

The example below shows an example of a digitized as-built survey. It is a combination of points and lines. When zoomed in close the labels to the structure type appear. Otherwise their symbology is a grouping of the structure form. The symbology has been simplified to group structure by form rather than have a unique symbol for every structure type. Form and the intended process linked to that form is more important to visually represent than the individual structure type. As-Built-Example

Surveying Protocol Layers Demo

Structure Points

Description- Locations of built structures as points. If lengths of structures are necessary use Structure Lines.

Structure Type:

AttributeStructure ClassDescription
ALSWood AccumulationAssisted log structure being a placed woody debris accumulation that does not include posts.
ALS - Bank AttachedWood AccumulationALS built extending from the bank towards the channel.
ALS - Bank BlasterWood AccumulationAn ALS oriented to enhance bank erosion.
ALS - Channel SpanningWood AccumulationALS built across the entire channel from bank to bank.
ALS - RhinoWood AccumulationALS built to the rhino structure design specification.
BDABeaver Dam AnalogThe general term describing a semi-permeable – channel-spanning structural element designed to mimic the form and function of a natural beaver dam.
BDA PostlessBeaver Dam AnalogA BDA constructed without the use of posts driven into the streambed that would be used to add stability to vegetative fill material.
Bag PlugsVegetation ProductionStructural treatment that uses bags made up of organic material, usually burlap, that can be filled with sediment and placed. Bag plug structures often mimic vegetative mases that might sluff into the channel.
Fell TreeWood AccumulationStrategic felling of a tree within a riverscape.
Floodplain BDABeaver Dam AnalogA BDA structure constructed on floodplain surfaces, i.e., not build in an existing active channel anabranch.
Floodplain LWDWood AccumulationPlacement of any large woody debris on the floodplain.
Full TreeWood AccumulationPlacement of an entire tree whether fell, grip hoisted or positioned using another means.
Grip Hoist TreeWood AccumulationA tree that has fallen or that could be fell and then repositioned as a structural element using a grip-hoist.
Headcut TreatmentOtherAny structural treatment intended to arrest headcut progression.
Leaky DamWood AccumulationA channel spanning accumulation of smaller woody material with a high degree of porosity.
One Rock DamZeedyk StructureA grade control structure build with a single layer of rock designed to stabilize the bed of channel by increasing roughness.
PALSWood AccumulationA post – assisted log structure, general term for a structural treatment constructed of woody debris secured in an accumulation by driving posts into the stream channel or floodplain.
PALS - Bank AttachedWood AccumulationPALS that are attached to the margin (bank) of the active channel. Generally intended to direct flow away from the attached bank and potentially encouraging bar formation and lateral erosion and/or migration of the active channel.
PALS - Bank BlasterWood AccumulationPALS that are oriented to direct flow into a bank to enhance rates and magnitudes of bank erosion.
PALS - Channel SpanningWood AccumulationPALS build with sufficient material to span an active channel. Generally intended to enhance channel aggradation rates and/or encourage floodplain connectivity.
PALS - Constriction JetWood AccumulationPALS that are constructed to direct flow into another non-erosive surface (boulder or armored bank) to enhance rates of bank or bed erosion.
PALS - Left Bank AttachedWood AccumulationA left bank attached PALS.
PALS - Mid ChannelWood AccumulationPALS built mid-channel, generally intended to enhance topographic complexity and bar formation.
PALS - RhinoWood AccumulationA specific PALS recipe used in large streams with high stream power. The structure is built to maximize contact with the stream bed and has a narrow upstream profile extending into a thick base downstream much like the horn of a rhino.
PALS - Right Bank AttachedWood AccumulationRight bank attached PALS.
Post and Brush PlugVegetation ProductionDensely packing small vegetation around rows of posts driven into the channel to form a channel spanning dam-like structure.
Postline Wicker WeaveBeaver Dam AnalogA variant of a BDA in which woody branches are woven between posts in a fashion similar to wicker furniture construction. Produces a flat dam structure with a thin longitudinal profile.
Primary BDABeaver Dam AnalogA large BDA that is generally designed and placed to have the greatest hydrologic and geomorphic impact. ‘Primary’ comes from beaver complexes that commonly contain one or more large pond-forming dams that are surrounded by smaller secondary dams.
RhinoWood AccumulationThe structure is built to maximize contact with the stream bed and has a narrow upstream profile extending into a thick base downstream much like the horn of a rhino.
Secondary BDABeaver Dam AnalogIn a complex of BDA structures, secondary BDAs are often constructed downstream a Primary BDA to dispute gradient or within non-primary or overflow channels.
Sedge PlugsVegetation ProductionCutting densely packed bricks of earth that are held together by sedges into the active channel spanning structure.
SpreadersZeedyk StructureA rock-lined depositional area designed to disperse channelized flow and restore sheet flow.
Strategic FellingWood AccumulationFelling of trees into the channel or floodplain.
Tight PALS (BDA without sod)Wood AccumulationA channel spanning PALS built of small woody material. Similar but more porous than a typical BDA.
Tree DamWood AccumulationA fell tree intended to act as a channel spanning dam, may have additional vegetative material, sediment, or sod additions to further decrease porosity.
Tree PlugWood AccumulationUsing a single large fell tree to create a channel spanning dam-like structure.
VanesZeedyk StructureAn in-channel structure usually constructed of posts and designed to induce meandering and point formation.
Wicker WeirsZeedyk StructureA specific PALS recipe used in large streams with high stream power. The structure is built to maximize contact with the stream bed and has a narrow upstream profile extending into a thick base downstream much like the horn of a rhino.
Wood JamWood AccumulationAnalogous to ALS being a placed accumulation of woody material that does not include driven posts.
Zuni BowlZeedyk StructureAn in-channel headcut control structure composed of rock-lined step falls and plunge pools intended to arrest the progression of headcuts.

Structure Lines

Description: location of built structures as lines. Suitable for use if delineating long structures such as a Primary BDA or if getting structure lengths is important.

Structure Type:

Same specifications as Structure Points

Observation Points

Description: any other relevant information about the survey that is worth leaving an annotation about.